Piling at Mayflower (II)

›
Bore piling works continue at the Mayflower site. A second traffic diversion was implemented mid-December at the junction of Street 11, swi...
Monday, 29 December 2014

Lentor D-walls & Piles

›
D-walling works at Lentor has commenced this quarter. Close to Yio Chu Kang road, the team is in the midst of constructing the sheet pile f...
Saturday, 27 December 2014

Tagore Piles & Excavates

›
Tagore is currently leading in progress due to the large number of equipment brought in by Leighton-John Holland. The ERSS along the south ...
‹
›