T201 - Structural Steel roof works at Mandai Bus Depot |
T202 - Painting of roof soffit at Concourse Level |
T203 - A&A works at NSL Woodlands Platform |
T205 - Under-platform SWC works |
T206 - Architectural works at CP/ES |
T208 - SWC works at Springleaf Concourse public area |
T208 - Entrance B escalator pit base slab completed |
T210 - Reinstatement of AMK Avenue 4 at Mayflower |
T210 - Completed railing installation at track access area |
T211 - Casting of tunnel base slab at launch shaft |
T212 - Block wall construction at concourse |
T212 - Upper Thomson platform slab |
T213 - Lower mezzanine level |
T217 - Casting of Napier base slab |
T218 - UT at subcon Starburst for entrance B underpass frame mining |
T219 - Removal of D-wall block wall at TBM interface at Orchard Boulevard |
T219 - Casting of base slab at platform link |
T220 - SWC bracket installation completed at GRW-ORC Woodlands bound |
T220 - Casting of internal wall at upper concourse level |
T221 - Roof slab rebar works at Havelock entrance A |
T223 - Roof slab waterproofing works at Maxwell Zone 2 |
T223 - Base slab completed at Zone G |
T223 - Internal wall construction at Maxwell Station |
T226 - Construction of internal wall at Marina Bay Upper Platform |
T226 - Construction of skin wall |
T226 - Commencement of ground freezing works |
T227 - TBM cutterhead dismantling at Marina Bay |
T228 - Dismantling and hoisting of TBM, removal of road decking for construction of entrance B |
T228 -- Base slab rebar works at Entrance A |
T228 - Internal RC wall construction at station |
All internal photographs in this post are taken by the respective LTA project teams.
No comments:
Post a Comment
Note: only a member of this blog may post a comment.