Excavation of the station has reached the formation level and casting of the underplatform/platform level are in progress. Excavation and RC works are simultaneously taking place across the entrances. TBM 1 has completed the second drive to Upper Thomson Station last month and dismantling works are in progress.
Completed concourse slab towards entrance D. Internal RC wall works for south TVF/VS/VE in progress. |
Service opening site behind entrance D |
Entrance C site |
RC works for cooling tower structure over entrance C |
RC works at the base slab of the station |
Entrance A |
Pipe jacking shaft backfilled at entrance B |
Excavation of entrance B |
Tunnel Chart for TEL1, December 2017 |