More About Us

Tuesday, 12 December 2017

Upper Thomson Cast (II)

Excavation of the station has reached the formation level and casting of the underplatform/platform level are in progress. Excavation and RC works are simultaneously taking place across the entrances. TBM 1 has completed the second drive to Upper Thomson Station last month and dismantling works are in progress.


Completed concourse slab towards entrance D. Internal RC wall works for south TVF/VS/VE in progress.
Service opening site behind entrance D
Entrance C site
RC works for cooling tower structure over entrance C
RC works at the base slab of the station


Entrance A
Pipe jacking shaft backfilled at entrance B
Excavation of entrance B
Tunnel Chart for TEL1, December 2017

No comments:

Post a Comment

Note: only a member of this blog may post a comment.