More About Us

Monday 18 September 2017

Upper Thomson Cast

Structure of the station is at varying progress with the basement roof and concourse slab cast at different zones. With the bored piling and ground improvement works completed, a total of 3 telescopic clamshell excavators are now facilitatating the excavation works for the top-down construction of the station. 


Upper Thomson Station
Entrance B site
Backfilling works taking place after the completion of the pipe jacking for the linkway


Excavation works around entrance A


Casting works completed at the basement roof and concourse levels

Excavation works to platform level

Excavation of station box

Excavation to concourse level
Commencement of excavation works around entrance D

Entrance D site
Entrance C site




No comments:

Post a Comment

Note: only a member of this blog may post a comment.