Excavation works for the station appears to have completed with structural works taking place at the platform level. Casting of the entrances are progressing, with the first superstructure emerging from Entrance D. Both TBMs are advancing through rock around Block 174 beneath AMK Avenue 4 and is targeted to breakthrough by December.
Lentor Station |
Ent C,D & E |
Entrance E |
RC works from subway to ground level |
Waterproofing to the completed roof of the underpass |
5XO Site |
Changi bound tunnel |
Tunnel roof slab cast |
Main drive of Changi bound TBM from 5XO to Mayflower |
Woodlands bound tunnel |