More About Us

Friday 7 July 2017

Napier Excavation (II)

Bulk excavation works continue at Napier station.


Excavation works at station box
Excavation works now at the S4 layer

Excavation works across station box and entrance A
Entrance A at S2 level
Excavation to S3
Final traffic alignment scheme till the end of the project
Napier station
Excavation and strutting works at north end of station
Relaunch of TBM S-930 scheduled by the end of the next quarter
Launch shaft
Preparation of upper slab
CP3 adit excavation works


No comments:

Post a Comment

Note: only a member of this blog may post a comment.