More About Us

Tuesday 18 April 2017

Shenton Way Cast (III)

Excavation works have reached the plantroom level and is progressing down to the upper platform level. Assembly of TBM 1 has completed and commencement of tunnelling works to Maxwell are slated to begin tomorrow.


Concourse slab completed at the station
LS3 with backup gantries connection on the surface
TBM 1 assembled up for the lower drive towards Maxwell
Looking up from the launch shaft
TBM Cradle
Final preparations for the commencement of the EPBM 
TBM will encounter the abandoned piles of the former UIC building during its initial drive, before undercrossing the EWL tunnels after advancing approximately 100 rings
Excavation & RC works at the station


View of the partially completed permanent monsoon drain structure cutting across the station roof beneath the gantry crane

Casting works for the plantroom level



Looking down from plantroom to Upper platform level
Upper platform level RC slab works


Sheet piling works for entrance C
Filling of temporary monsoon canal for the linkway construction and entrance B&C
LS4 handed over back to the T225 team earlier this month upon completion of the upper slab structure
Re-launch of TBM 2 on the Changi bound drive is slated by June

No comments:

Post a Comment

Note: only a member of this blog may post a comment.