Excavation works have reached the plantroom level and is progressing down to the upper platform level. Assembly of TBM 1 has completed and commencement of tunnelling works to Maxwell are slated to begin tomorrow.
Concourse slab completed at the station |
LS3 with backup gantries connection on the surface |
TBM 1 assembled up for the lower drive towards Maxwell |
Looking up from the launch shaft |
Final preparations for the commencement of the EPBM |
TBM will encounter the abandoned piles of the former UIC building during its initial drive, before undercrossing the EWL tunnels after advancing approximately 100 rings |
Excavation & RC works at the station |
View of the partially completed permanent monsoon drain structure cutting across the station roof beneath the gantry crane |
Casting works for the plantroom level |
Looking down from plantroom to Upper platform level |
Upper platform level RC slab works |
Sheet piling works for entrance C |
Filling of temporary monsoon canal for the linkway construction and entrance B&C |
LS4 handed over back to the T225 team earlier this month upon completion of the upper slab structure |
Re-launch of TBM 2 on the Changi bound drive is slated by June |