More About Us

Monday 19 September 2016

Stevens D-walls (IV)

D-walling works progresses at the Stevens station. TBM 1 and TBM 2 have completed initial drive works and are transitioning to the main drive, while TBM 3 has just started tunnel excavation works.


T216 Stevens Station site










Entrance A

Entrance C&D & Escalator shaft
Escalator shaft adjacent to the Downtown Line station












Dalvey Launch Shaft


STP
Backup gantries
Acoustic Shed


TBM 4 cutterhead lowered and TBM assembly

TBM 2 main drive conversion (dismantled temporary rings)
Initial drive of TBM 2 (August 2016)

Advancement works during excavation

Ground improvement works by T216 team at Napier
Launch shaft 10 at Mount Pleasant station
TBM 3 initial drive commenced on Woodlands bound tunnel towards Stevens

STPs

Transitioning to main drive for TBM 1 (August 2016)
TBM 2 prior to launching

Installation of raised platform


No comments:

Post a Comment

Note: only a member of this blog may post a comment.