More About Us

Friday 17 June 2016

Orchard Boulevard Reinstatement

Construction of the plenum roof has completed and the team is now preparing to reinstate the traffic along Grange Road and Orchard Boulevard prior to the commencement of the top-down excavation.


RC works for permanent culvert and footpath over the completed station roof
Excavation pit 1 alongside the footpath under reinstatement







No comments:

Post a Comment

Note: only a member of this blog may post a comment.