D-walling works continue at the Lentor station following the realignment of Lentor Drive. The first TBM has commenced the initial drive on the Changi bound tunnel towards the 5XO site, which is nearly completed with excavation works.
Realignment of Lentor Drive |
Bored pile construction |
Trencing of Diaphragm wall |
Pouring of roof slab |
May 17 |
June 5 (Photo cr: Arnel) |
Earth retaining sheet pile for linkway and entrance |
Noise enclosure installed at the launch shaft for residents across the road |
Launch of the first TBM drive down AMK avenue 4 |
Excavation completed at the north section of 5XO |