More About Us

Monday, 20 June 2016

Havelock Diverts

The second traffic diversion along Zion road for the secant bored pile works along the Havelock station has been implemented. The final stretch of SBP construction along the east side of the station is underway. A second diversion along Havelock Road has also taken place for the grouting works along the rectangular TBM drive, which will complete around end-September.


Diversion along Zion Road for the SBP works









Rectangular TBM drive towards the station box



Traffic diversion along Havelock Road for the grouting works in front of Holiday Inn
Precast yard

22 segments have been pushed into the ground as of June 16
The machine will reach the Havelock station by Sep/Oct at the present advance of 1 ring a day

No comments:

Post a Comment

Note: only a member of this blog may post a comment.