The second traffic diversion along Zion road for the secant bored pile works along the Havelock station has been implemented. The final stretch of SBP construction along the east side of the station is underway. A second diversion along Havelock Road has also taken place for the grouting works along the rectangular TBM drive, which will complete around end-September.
|
Diversion along Zion Road for the SBP works |
|
Rectangular TBM drive towards the station box |
|
Traffic diversion along Havelock Road for the grouting works in front of Holiday Inn |
|
Precast yard |
|
22 segments have been pushed into the ground as of June 16 |
|
The machine will reach the Havelock station by Sep/Oct at the present advance of 1 ring a day |