Piling at Napier (V)

Piling works continue at the Napier station.

Continuation of the SBP wall construction at Napier


Preparations for the impending diversion of the city bound carriageway












Backup gantries connected to the Herrenknecht mixshield S-930 inside the launch shaft, which is believed to commence tunnelling this month