More About Us

Sunday, 20 December 2015

Caldecott Excavation (III)

Excavation works are nearly completed at the Caldecott Station. 6 layers of struts have been installed across the span of the station. Similarly on the opposite end of Toa Payoh West, the southern section of the cripple siding tunnel has almost reached the formation level and a gantry crane has been installed to facilitate the remaining muck removal and subsequent mining works.
























No comments:

Post a Comment

Note: only a member of this blog may post a comment.