More About Us

Friday, 16 October 2015

Marina Bay D-walls (IV)

D-walling and ground improvement works continues at the Marina Bay station. The launch shaft seems to have completed excavation works and seems to be in the midst of preparation for the impending handover to T225. A separate shaft to the south is currently being excavated for the future mining of the linkway between TEL and NSL station, beneath the existing NSL and CCL tunnels, which will connect between this shaft and the TBM launch shaft.





















No comments:

Post a Comment

Note: only a member of this blog may post a comment.