The Pedestrian Overhead Bridge along Outram Road was successfully demolished on May 24 and most recently July 12 along the CTE bound and Cantonment bound carriageway respectively. This is the 4th POB to be demolished along Thomson Line project. In addition to preparations works for the upcoming numerous road diversions for the construction of the interchange linkway is the relocation of the ERP gantry along Eu Tong Sen Street.
Majority of the shops within Pearls Centre have started to vacate following the management's decision to cease all tenure lease by the end of this quarter. Demolishment of the complex can be expected by the first half of next year. D-walling and piling works continue around the site area.
Column remain of the demolished POB linking HSA to the existing station |
Relocated ERP gantry down the road |