The first traffic diversion at the Napier site was implemented earlier this morning. One of the major TD along the Thomson Line project, the westbound carriageway has swung away from Gleneagles and now runs alongside the launch shaft.
Photos were taken in the week leading up to the diversion.
|
July 25 - Diversion of westbound Napier and Holland road |
|
July 17 - Earthworks |
|
July 21 - Surfacing |
|
July 23 - Curve setting for the diverted road over the former lane 4 |
|
Painting and installation of the new covered linkway |
|
July 25 - Midnight preparations |
No comments: