Piling works continue at the Havelock site. A temporary retaining wall has been created to counter the uneven terrain between the HDB flats and Zion Road. The piling rigs are situated on the higher elevation next to the flats.
A rectangular CREG TBM will be utilized to construct the pedestrian underpass between the station and the entrances at Havelock Road. DCM works have commenced across Havelock Road where the launch shaft for the TBM is to be located.
Retaining wall between the hilly terrain and the road level |