More About Us

Tuesday 23 December 2014

Facility Building Reduces Level

Slope treatment works continue at the RTS Facility Building. The site is currently being excavated to match the reduced level of the Seletar Expressway. Upon completion, piling works will commence on the RTS shaft and subsequently excavation. The site office has also been completed along Upper Thomson Road beside the Springleaf site. The escape shaft site between the RTS and SBAB has been cleared, though no works on the ERSS have commenced. 4 Japanese EPB machines have been said to be procured for this contract, instead of the initial recommendation of slurry TBMs.


Excavation of the RTS Facility Building site
Bentonite Plant
T207 Escape shaft south of SBAB and MDD
Site access along Mandai Road

October 8 - RTS




No comments:

Post a Comment

Note: only a member of this blog may post a comment.