As the existing Woodlands Drive 16 cuts through the Woodlands South site, an interim road has been created to go around the site area. The road however has not yet been opened to public. Works are also underway for another road diversion along Avenue 1. The road will be shifted closer to Christ Church Secondary - this is to facilitate the construction of the station's earth retaining stabilizing structure (ERSS).
Northern end of station box where a road diversion for Avenue 1 is being prepared |
The woodlands South site office is powered by solar panels. SBAB can be seen at the left background |
New junction of Avenue 1/Drive 16 |
SBAB in the background |
The new Woodlands Drive 16 will go around the new site |
New Drive 16 |
Unopened Drive 16 |
Station box |
Bentonite Silos |