Friday, 1 September 2017
Woodlands North Cast (V)
›
Structural works for the station box are largely completed at the roof level and BSC is targeted by the end of the year. Casting of the nor...
Tuesday, 1 August 2017
August Tunnel Progress
›
The 2km long twin tunnels between Springleaf station and the RTS Facility Building have completed under the T207 project. These are the lon...
Wednesday, 19 July 2017
Gardens By The Bay - TBM Reassembly
›
Tunnelling works for the Woodlands bound tunnel has completed from Gardens by the Bay station to the Marina East shaft, where the TBM has U...
‹
›