Thomson Line Construction

8 Year documentation on the making of the Thomson Line

More About Us

▼
Friday, 30 June 2017

Upper Thomson Excavation

›
D-walling works for the station was completed earlier this quarter and the associated silos have been dismantled. Bored piling works for th...
Thursday, 29 June 2017

Bright Hill Excavation (II)

›
Excavation works at the station box are ongoing to the platform level, with the concourse slab completed. The Woodlands bound tunnel to May...
Wednesday, 28 June 2017

Mayflower Cast (IV)

›
Structural works for the station and entrances are largely completed. A realignment of Street 11 has taken place for the construction of th...
‹
›