Friday, 30 September 2016
Great World Cast
›
Construction of the roof slab is taking place and is midway completed at the Great World station. Excavation works have commenced at the no...
Thursday, 29 September 2016
Orchard Cast (II)
›
D-walling works for the project have been fully completed at the cut and cover tunnel ahead of schedule and excavation works have commenced...
Tuesday, 27 September 2016
Orchard Boulevard Excavation
›
Top-down construction of the Orchard Boulevard Station have commenced with excavation works reaching the roof slab. Concreting works will t...
‹
›