Saturday, 21 May 2016
May Tunnel Progress
›
The second bored tunnel was completed at the T208 project earlier this month, lining the Changi bound tunnel between Tagore and Lentor. Des...
Tuesday, 19 April 2016
Gardens By The Bay Excavation
›
Excavation works are now underway at the station box. The diaphragm wall of the GBME shaft was completed in January and a pile test is curr...
Monday, 18 April 2016
Marina South Excavation (II)
›
Excavation works commences at the cut and cover tunnel, and continues within the Marina South station box. The formation level at the launc...
‹
›