8 Year documentation on the making of the Thomson Line

More About Us

▼
Monday, 14 March 2016

Mount Pleasant Excavation

›
The bored piling works are wrapping up and the piling rigs are gradually being demobilized. Casting of the capping beam for perimeter of th...
Sunday, 13 March 2016

First Tunnel Completes

›
The first TBM that was launched from Tagore in August last year has completed excavation works at the Lentor station. The NFM-made slurry m...
Saturday, 12 March 2016

Caldecott Excavation (IV)

›
Excavation at the Caldecott station is nearly completed, and mining works for the Thomson Cripple Siding have commenced from the south cut a...
‹
›