Friday, 31 July 2015
Gardens By The Bay D-walls (III)
›
Works on the diaphragm wall continues at the Gardens By The Bay site. Site clearing has commenced at the GBME retrieval shaft. Excavat...
Wednesday, 29 July 2015
Piling at Marina South
›
Piling works commenced at Marina South in the 2nd quarter of this year, the last of the 25 contracts to do so. Ground improvement works hav...
Monday, 27 July 2015
Marina Bay D-walls (III)
›
D-walling works continue at the Marina Bay site alongside further ground improvements. The launch shaft at the north end of the station has...
‹
›