Gardens By The Bay D-walls (II)
›
Concluding our first quarter updates for the Thomson Line at the Gardens by the Bay station, D-walling works on the station box continues w...
Tuesday, 21 April 2015
Marina South - Deep Cement Mixing (II)
›
The cut and cover tunnel to Gardens by the Bay which have been hoarded up, now elongates the worksite boundaries of the T227 project parall...
Monday, 20 April 2015
Marina Bay D-walls (II)
›
Works on the diaphragm wall continues around the Marina Bay station box. Hoardings for the project boundary have been extended along the ex...
‹
›