Thomson Line Construction

8 Year documentation on the making of the Thomson Line

More About Us

▼
Saturday, 31 January 2015

Gardens By The Bay D-walls

›
Guide walls for the diaphragm wall trench have been installed around the perimeter of the station box, where D-walling works are underway. ...
Friday, 30 January 2015

Marina South - Deep Cement Mixing

›
The site at Marina South has hyped up in construction activities with the commencement of Deep Cement Mixing and pipe piling works. Above t...
Wednesday, 28 January 2015

Marina Bay D-walls

›
Intensive ground improvement works are taking place around the Marina Bay site, concurrent with the D-walling. Kori will supply and facilita...
‹
›
Home
View web version

Author

Nethaniel
View my complete profile
Powered by Blogger.