Friday, 30 June 2017

Upper Thomson Excavation

D-walling works for the station was completed earlier this quarter and the associated silos have been dismantled. Bored piling works for the station's foundation are taking place at the south side of the station, while excavation works on the north end has reached the concourse level.


Bored piling works around entrance D

Thursday, 29 June 2017

Bright Hill Excavation (II)

Excavation works at the station box are ongoing to the platform level, with the concourse slab completed. The Woodlands bound tunnel to Mayflower has presumably been completed by TBM 4, and the remaining 3 TBMs are anticipated to complete by the next quarter.


Ground improvement works at the extracted H-pile foundation of the former POB along Upper Thomson Road

Wednesday, 28 June 2017

Mayflower Cast (IV)

Structural works for the station and entrances are largely completed. A realignment of Street 11 has taken place for the construction of the underpass link from the station to entrance D.


Basic structure completed at entrance D & realignment of AMK St 11 for the remaining subway construction

Tuesday, 27 June 2017

Lentor Cast (III)

Construction of Entrance C has started adjacent to the launch shaft. Excavation works for the station is almost completed with structure of the platform level presumably taking shape.


Construction of Entrance C,D and E

Tuesday, 20 June 2017

Tagore Backfill

Filling works are in progress over the completed structure at Tagore which would site the 1 hectare trackworks staging ground to come. The final TBM C2 is about 75% completed and will complete by the next quarter.


Backfilling works and de-strutting over the concourse slab 

Springleaf Cast (II)

Structure of the Springleaf station is taking shape with the first section of roof slab completed.


Springleaf station

Sunday, 18 June 2017

Facility Building Cast (III)

The full face rock conditions experienced by the final 2 EPBMs from Springleaf have significantly hindered the progress over the last quarter with an average advancement rate of a single ring building per day. TBM 1 is about 30 rings from breakthrough and should complete within a month's time.


Tower crane erected to facilitate the RC works of the facility building superstructure

Saturday, 17 June 2017

TEL1 Tunnelling Completes

Bored tunnelling works have completed this month under Stage 1 of the project between Woodlands North, Mandai Depot and the Sembawang Airbase cut and cover tunnel site. 12 tunnel drives were launched using 3 Earth Pressure Balance machine 4 Slurry TBMs which bore through the weathered Bukit Timah Granite to complete the 8km network of mainline and reception tunnels beneath Woodlands.

For most of the tunnels, the basic structural completion (BSC) have already been achieved with the first stage concreting (FSC) for the track bed, together with brackets installation for the various SWC. Trackworks are slated to commence through the tunnels by the end of 2017, with the remaining SWCs gaining access from the 2nd half of 2018.


Mandai Depot Stabling Yard

Tuesday, 13 June 2017

Woodlands South Cast

Concourse slab of the station structure has been cast and excavation works are progressing down to the platform.


Excavation works of UPC to the future Woodlands Health Campus

Woodlands Cast (III)

Casting of the concourse level is midway completed across the station box, while excavation works at Entrance F, G and the subway link within the bus interchange have commenced.


T203 Woodlands site

Woodlands North Cast (IV)

Casting of the concourse slab at the station is largely completed and structural works are progressing up to the roof level of the station. The south crossover tunnel is completed and filling works are taking place to the roof level. Structural works on the overrun tunnel are underway.


Filling works at the completed south crossover tunnel