Tunnelling works are underway along all the projects along stages 1 and 2 of the line, with the first slurry TBM for the T211 project launched at Bright Hill this week. 5 bored tunnels have been completed by the first half of the year and a further 5-8 tunnels are envisaged to complete by year end.
TEL1/2 Tunnel Chart, July 2016 |
T206 - Launch preparations for the second drive of TBM 4 for reception tunnel 1 at Sembawang Airbase C&C (Photo credits: LTA) |