Thursday, 18 June 2015

Updates Postponed

In the midst of upgrading our blog equipment, the remaining updates of the line will be indicatively postponed till the end of the month.

Edit: Updates for Bright Hill to Gardens By the Bay will resume in July.

Tuesday, 16 June 2015

Piling at Mayflower (IV)

Piling works at the Mayflower Station are now about 60% completed. The third traffic diversion along Avenue 4 was implemented earlier this month. The realigned road to the east now allow for piling to be done on the west side of the station box. The diversion is envisaged to last for 3 months. Grouting is taking place on the south side of the station as well.


Stage 3A Traffic Diversion

Monday, 15 June 2015

Lentor Excavation

Excavation works have commenced on the north face of the station box. The outline of the launch shaft at the south end of the station is evident too, and we can expect excavation of the shaft to commence by the third quarter of this year. The linkway to the Calrose entrance seems to have completed excavation to the formation level where 3 layers of struts have been installed.

D-walling works continue at the 5XO crossover site along Ang Mo Kio Avenue 4.


Lentor Station
D-walling at 5XO