Tuesday, 19 April 2016

Gardens By The Bay Excavation

Excavation works are now underway at the station box. The diaphragm wall of the GBME shaft was completed in January and a pile test is currently being carried out on the surface. Excavation of the retrieval shaft would commence by the 2nd quarter.


Shoring and decking works for the first strut layer at the Gardens By The Bay station

Monday, 18 April 2016

Marina South Excavation (II)

Excavation works commences at the cut and cover tunnel, and continues within the Marina South station box. The formation level at the launch shaft has been reached and casting of the base slab is proceeding. An assembled gantry crane accompanied with the delivered CREG earth pressure balance TBM sits adjacent to the shaft surface. 

Marina Boulevard has been decked and realigned for the remaining pipe pile construction.


Commencement of shoring works for the T227 cut and cover tunnels

Sunday, 17 April 2016

Marina Bay Excavation (II)

The roof slab of the station has been fully concreted and excavation for the top-down construction of the station progresses. 2 separate updates taken in March and April have been compiled in this post.


March 8