Saturday, 25 June 2016

Marina South Excavation (III)

Bulk excavation works are underway at the station and cut and cover tunnels. The remaining pipe pile construction is being carried out beneath the former Marina Boulevard.


Excavation works at the cut and cover tunnel

Friday, 24 June 2016

Marina Bay Cast

RC works for the concourse slab are in progress at the Marina Bay station, while piling works commence for the interchange linkway to the North South Line. Sheares Avenue have opened between Maxwell Road and Central Boulevard, providing an interim linkage within the restricted zone of the CBD. The permanent road will be realigned towards the end of the project, and will be served by Entrance B and 2 ventilation buildings under the TEL project.


Opening of Sheares Avenue by the T226 team

Thursday, 23 June 2016

Shenton Way Cast

Excavation of LS3 have commenced within the Shenton Way station, of which the bored pile works are still progressing. The roof slab is being prepared for sequential casting and rebar installation is in progress. TBM 2 has commenced its initial drive at LS4 following the commencement of tunnelling works earlier this month.


Top-down view of the station box with its roof slab progressively being constructed concurrent with the bored pile foundation works